When a software system fails to perform the functions for which it was commissioned, the question is whether the failure is a development defect or whether the missing functionality was never included in the specification. Responsibility for a failed project depends on the parties’ contractual obligations, the causes of the failure and the allocation of risk under the agreement.
Software development disputes differ from ordinary commercial claims because determining liability may require an examination of source code, system architecture, computing infrastructure, development processes and testing. This is a particular feature of technology and internet litigation. This article addresses disputes arising after the agreement has been concluded. The contracting stage is discussed separately in our guide to software development agreements.
When Does a Failed Software Development Project Constitute a Breach of Contract?
Section 1 of the Contracts (Remedies for Breach of Contract) Law, 5731-1970, defines a breach as an act or omission contrary to the contract. The initial question is therefore what each party undertook to do, rather than whether the system ultimately delivered the commercial benefits the customer had hoped to obtain. An undertaking to deliver an operational system with a defined scope by a specified date differs from an undertaking to provide development hours by qualified personnel for a project whose outcome has not yet been defined.
The Contract for Services Law, 5734-1974, may apply where a person who is not the customer’s employee undertakes to perform work or provide a service for remuneration. Sections 1 and 2 establish the contractor’s obligation to perform the work or service and the customer’s obligation to pay the agreed consideration. Under section 8, the Law is subject to specific statutory provisions and any contrary intention apparent from the agreement. A contract for the supply of an asset to be produced or manufactured is governed by the Sale Law where the contractor undertakes to supply the principal materials required for its production. The classification of a software transaction combining bespoke development, the purchase of an existing product, licensing and implementation depends on the components of the transaction and the terms of the contract.
A failed implementation may result from an unsuitable architectural decision, insufficient expertise within the development team, incompatibility between systems or the customer’s failure to provide data. In some cases, the failure reflects a risk the parties knew about and agreed to bear. A distinction must also be drawn between a breach of a development obligation and the commercial failure of a completed product. A developer who undertakes to deliver a functioning application does not, by that undertaking alone, guarantee that the application will attract the number of users or generate the revenue projected by the customer.
The Scope of the Developer’s Obligations and Interpretation of the Agreement
The contractual deliverables must be identified from the agreement and its constituent documents: the quotation, requirements specification, statement of work, work plan, milestones and acceptance criteria. It is necessary to establish which version of the requirements document was approved, its position in the contractual hierarchy, any agreed assumptions and the items excluded from the contract price. The binding effect of a technical document depends on what the parties agreed.
Amendment No. 3 to the Contracts (General Part) Law, 5733-1973, published on January 7, 2026, amended section 25(a) in respect of contracts concluded or renewed after the amendment came into force. The provision allows the parties to agree on the method of contractual interpretation and the evidence admissible for that purpose. In the absence of such an agreement, a business contract is interpreted solely according to its wording, unless a textual interpretation produces an unreasonable result or reveals a contradiction between its provisions. Where either exception applies, the other interpretive rules under the section apply. Separate rules govern standard form contracts, non-business contracts and employment contracts. Parties who were not represented by a lawyer in drafting the contract are treated, for the purposes of section 25(a)(1), as not having agreed on the method of interpretation. The previous version of the section applies to a contract concluded before the amendment and not renewed after it came into force.
The admissibility and significance of a sales presentation or pre-contract correspondence in interpreting the specification of a business contract are determined under section 25. A subsequent agreement to modify the parties’ obligations must be considered separately from interpretation of the original contract. Relevant questions include whether an authorised person approved the change in scope, whether written approval was required and whether the parties’ conduct establishes a binding amendment. Misrepresentation during negotiations or breach of the duty to negotiate in good faith may also provide an independent cause of action, subject to sections 12 and 15 of the Contracts (General Part) Law.
In Civil Case (Tel Aviv Magistrates’ Court) 25019-06-11 Buy the People Ltd. v. Midas 3X Israel Ltd., paras. 11-18 (June 14, 2012), a development services provider sued for payment. The agreement specified an hourly rate rather than an undertaking to complete a particular system or to finish development by a particular date. The court rejected the argument that an estimated duration in a specification prepared after execution of the agreement constituted a binding completion date. It also found that the work had not been completed because the customer had stopped paying. In an hourly engagement, the provider’s performance is assessed against the quality, professional and delivery obligations it actually assumed.
Software Delivery Delays and Budget Overruns
Whether a target date in a work plan is binding depends on the terms of the engagement, the milestone arrangements and any dependencies on information, infrastructure or approvals from the customer. Even where a binding deadline has been missed, delays attributable to the developer must be distinguished from those caused by the customer. Section 43 of the Contracts (General Part) Law provides, among other things, that the time for performance is postponed where performance is prevented by a circumstance attributable to the creditor, or where performance is conditional upon a prior obligation of the creditor that has not been fulfilled.
In Agile projects, requirements are specified and prioritised in short development cycles. Reprioritising requirements or dividing one task into several does not necessarily expand the scope. Adding a module, moving to another operating environment or substantially modifying a calculation mechanism may, however, require new work. The specification history must be reconstructed, defect correction distinguished from change requests, and any agreement concerning the effect of a change on price and schedule examined.
In a fixed-price project, a provider who underestimated the effort required to complete the agreed scope is not entitled to additional payment merely because of that error. In an hourly contract, exceeding an estimate does not necessarily constitute a breach, but the provider may have undertaken to observe a budget cap, obtain prior approval or give advance warning. Where the provider discovers that its chosen architecture will prevent completion within the agreed constraints, continuing to charge the customer without disclosing the difficulty may give rise to a claim for breach or bad faith in performance under section 39 of the Contracts (General Part) Law.
In Civil Case (Tel Aviv District Court) 47012-06-17 Hameshavev H.M.T.S. Ltd. v. Complete Business Solutions Ltd., paras. 26-38 (June 20, 2022), the court examined an ERP implementation project that had exceeded its planned duration and budget. The agreement was classified as a relatively open-ended relational contract that did not expressly allocate the risk of project failure. From the purpose of the transaction, the implementer’s expertise and the fact that the implementer had proposed the budget and timetable, the court inferred that the implementer bore the risk of failure arising from substantial overruns, unless the failure was clearly attributable to the customer. The court also held that successive delays and failures could cumulatively amount to a breach, even where an unsuccessful pilot would not in itself do so. The contract was interpreted under the law preceding Amendment No. 3 to the Contracts Law.
Software Defects and Failed Acceptance Testing
Software conformity is assessed against the agreed requirements. A system that runs successfully in a development environment may fail in production when required to handle substantial loads, migrated data or complex permissions. If performance, security or compatibility requirements were agreed, the system must also meet them. Conversely, the absence of a function outside the agreed scope is not a defect merely because the customer needs it after launch.
User acceptance testing (UAT) is intended to establish whether the deliverables satisfy the requirements before the customer approves delivery or progression to the next stage. Where payment is conditional upon acceptance testing, it is necessary to establish whether the agreed test scenarios were used, whether the defects justified rejection and whether the provider was entitled to deliver the system with non-critical defects. Approval of a milestone or commercial use of the software is relevant evidence of delivery but does not necessarily preclude a claim concerning a latent defect, a warranty obligation or an outstanding contractual obligation.
Where the Contract for Services Law applies, section 3 requires the customer to notify the contractor of a defect within a reasonable time after discovering it or when it ought to have been discovered, and to give the contractor a reasonable opportunity to remedy a remediable defect. Failure to comply may prevent the customer from relying on the defect unless the contractor knew of it. The customer cannot rely on a defect attributable to a cause for which the customer is responsible. Subject to its conditions, section 4 permits the customer to remedy a defect and recover reasonable repair costs, or to deduct the reduction in the value of the service from the remuneration while the defect remains unremedied. An urgent defect that cannot await repair by the contractor may justify immediate repair, and an irremediable defect may justify a deduction. Section 7 preserves other remedies for breach of contract.
In Civil Case (Rishon LeZion Magistrates’ Court) 7229-01 Shaked Computers and Data Processing Ltd. v. Z-Tech Computers Ltd., paras. 94-96 (May 20, 2012), a claim concerning the development of a software system was dismissed. After difficulties arose in the project, the parties agreed that the software and source code would be delivered in their existing condition, subject to the absence of critical failures, for reduced consideration. The court held that the later agreement superseded the original software delivery obligation and did not preserve claims under the earlier contract. It noted that, had the original agreement remained in force, there would prima facie have been grounds for finding that the developer had not performed its obligations properly. As no breach of the new agreement was established, the claim was dismissed. An agreement ending development or transferring a project to another provider should therefore expressly state whether it governs delivery alone or also settles financial claims arising from earlier breaches.
The Customer’s Responsibility for Project Failure and the Developer’s Claim for Payment
Software projects generally require cooperation from the customer, who understands the business processes, approves specifications, provides migration data and allocates personnel for acceptance testing. Where decisions are delayed or inaccurate data is supplied, their effect on the work schedule and the provider’s ability to perform must be assessed. A professional provider should nevertheless identify such dependencies when they arise and explain their implications to the customer, rather than attributing all delays to the customer after the event.
A provider’s claim for payment may be based on hours worked under the contract, completion of a milestone or approved additional work. Relevant questions include whether payment depends on delivery or acceptance, whether previous invoices were approved and how working hours were calculated. Where a customer seeks to set off damages against an invoice, the source of the debt and the requirements of section 53 of the Contracts (General Part) Law must be examined alongside any contractual set-off provision. Calculation of the outstanding consideration must account for any deduction to which the customer is entitled in respect of a defect and any debt available for set-off.
In Buy the People (paras. 8, 15-22 and 27-35), access to the system was blocked pursuant to a contractual right of retention. The claim was allowed and the customer company and its manager were held jointly and severally liable for the amount claimed. The manager’s personal liability arose from findings that he had knowingly and in bad faith decided not to pay without substantive justification, while continuing to receive work without raising his objections at the time.
Conversely, shutting down an operational system or denying access to deliverables for non-payment may itself constitute a further breach if unsupported by the contract or the law. The continuing service obligation, right of suspension, software usage rights and obligation to permit access to business data already generated must be examined separately. Disputes concerning continuity of cloud services and data transfer may raise additional contractual issues, discussed in our guide to SaaS agreements and cloud services.
Termination of a Software Development Agreement
Sections 6-8 of the Contracts (Remedies for Breach of Contract) Law distinguish a fundamental breach, which confers a statutory right to terminate without granting an extension for performance, from a non-fundamental breach, which generally requires an extension before termination. Where a non-fundamental breach remains unremedied after the extension, the question whether termination is unjust may still arise under section 7(b). A fundamental breach includes a breach that would have caused a reasonable person not to enter into the contract had they foreseen the breach and its consequences, or one designated as fundamental by the contract. A blanket provision treating every breach as fundamental is effective only if reasonable at the time of contracting.
In an inventory management system, a failure preventing real-time inventory management may affect the core of the transaction in a way that a repairable report display defect does not. The delivery date may be decisive if the provider undertook to complete the system before a known commercial event.
Termination is effected by notice within a reasonable time after the breach becomes known, or after the expiration of the extension where applicable. Section 7(c) governs termination of a divisible contract. In a multi-stage project, a completed module may be usable independently even if another has failed; it is necessary to determine whether the contract is divisible and whether the breach justifies termination of the whole contract. Continued payments, approval of deliverables and addition of requirements for months after an alleged breach may raise questions about whether the reasonable period for termination has expired and whether the parties agreed to continue the work. An unjustified termination notice may itself give the other party a cause of action.
Delivery of Source Code and Continuation of Development by a Replacement Provider
Rights in the source code and rights to use the software after termination are determined by law and the contractual provisions governing assignment, the timing of the assignment, any payment conditions and the scope of the licence. Delivery of a copy of the code must be distinguished from assignment of its copyright, and code developed for the project from libraries and tools the provider brought to the engagement. Israeli law distinguishes employee works from commissioned works under sections 34 and 35 of the Copyright Law, 5768-2007. Section 37 requires a written document for an assignment of copyright or the grant of an exclusive licence. These issues are discussed in our guide to software copyright in Israel.
In practice, a replacement provider may need not only the source code but also version history, build and installation instructions, the database schema, configuration files and authorised access to computing environments. Deliverables that cannot be built or run without the original provider’s services may have little practical value even if a file containing code has been delivered. The right to receive these components depends on the delivery obligations and rights acquired. A customer may seek specific performance of the obligation to deliver existing work and an order preserving it where necessary for the litigation. By contrast, an order compelling a provider to complete an ongoing development project may be subject to the exceptions to specific performance in section 3 of the Remedies Law, including personal services, impossibility of performance or the need for unreasonable judicial supervision.
Restitution and Damages for a Failed Software Development Project
Under section 9 of the Remedies Law, termination gives rise to reciprocal restitution of what the parties received under the contract, or its value, subject to the statutory conditions. In determining restitution for an unfinished project, the value of the deliverables and the extent of the termination must be assessed. Their value also depends on whether software components remain usable or can be incorporated into development by another provider.
Section 10 confers a right to compensation for loss caused by the breach and its consequences that the breaching party foresaw or ought to have foreseen, at the time of contracting, as a probable consequence of the breach. A significant head of loss is the reasonable cost of completing or repairing the system through another provider. The estimate should distinguish the cost of obtaining the original deliverable from upgrades the customer chose to add after termination, and account for amounts that remain unpaid under the original agreement. Expenditure on data migration, employee training and implementation may also be relevant if wasted as a result of the breach.
Lost profits may be substantial where the system was intended to replace an expensive business process or serve as a product sold to customers. The claimant must establish how the software failure caused the lost profits; a revenue forecast prepared before contracting is not sufficient. Where the system was intended to improve existing operations, sales data, operating costs and comparisons with the period in which the previous system was in use may provide a stronger basis for assessment. Future profits from a new product are harder to establish. Signed orders, comparable business data and costs saved by not launching are relevant to estimating net profit rather than projected turnover.
Where profits that would have been earned through performance cannot be established, reliance damages may be claimed in the alternative for expenditure and investment wasted as a result of the breach. In Civil Appeal 322/06 Compaq Computers (Israel) Ltd. v. Hagar Management and Manpower Services Ltd., paras. 6, 11-12 (December 3, 2007), the court considered a breach of a cooperation agreement for a computing project in anticipation of a tender. The software company’s claim for expectation damages in respect of anticipated profits was rejected because it had not established that it would have won the tender but for the breach. The Supreme Court upheld reliance damages of USD 200,000 for expenditure and investment in developing the system, and a further USD 50,000 for harm to goodwill. Assessment of reliance damages took account of the controlling shareholder’s testimony, the competing company’s investment data and the purpose of the cooperation agreement, which included the trial phase preceding publication of the tender. The Supreme Court gave weight to the impaired prospects of winning the tender and the difficulty in assessing those prospects caused by the breach. The judgment illustrates how development expenditure can support a damages claim even where the project’s anticipated profit cannot be established. Development costs should accordingly be documented by project stage, including developer salaries, subcontractor payments and implementation expenditure, distinguishing investments made for the engagement from earlier product development costs.
Damages must be calculated without double recovery. A customer who has recovered the entire consideration cannot disregard that recovery in calculating the cost of a replacement transaction. Section 14 of the Remedies Law excludes compensation for loss that could have been avoided or reduced by reasonable measures and provides for recovery of reasonable mitigation expenditure. Section 15 permits agreed damages without proof of loss, subject to the court’s power to reduce the amount if it bears no reasonable relationship to the loss that could have been foreseen when the contract was concluded as a probable consequence of the breach. Where the contract contains a liability cap, exclusion of lost profits or service credit mechanism, their application to the particular breach and remedy sought, and their enforceability under the applicable law, must be examined.
Proving Breach of a Software Development Agreement and Expert Evidence
A development dispute requires reconstruction of the software’s condition at delivery, particularly if the code has since changed. To assess alleged non-conformity, the relevant code version, delivery date, operating environment and test data must be identified. Git version history, deployment logs, automated test results and defect records can help reconstruct the state of the software, subject to authentication of their source and integrity.
Project management systems can show when a requirement was added, what was specified as an acceptance criterion, when a defect was discovered and to whom it was assigned. Timesheets help establish the extent of the work, alongside records linking hours worked to the commissioned scope and closed tasks to delivered work. Correspondence, version approvals and acceptance records supplement technical documentation and link the work performed to the relevant contractual obligation.
An expert opinion should address defined questions: whether the software conforms to the binding specification, whether the failure can be reproduced, what caused it, whether it can be remedied and how much work is required. In Hameshavev (para. 36), the court found that the opinions submitted by both parties were expressed in general terms and supported the positions of the parties that had commissioned them, but did not materially assist in determining the causes of failure. General criticism of code quality is insufficient without a link between the defects and the obligations breached. An expert examining a system in a test environment should explain how it differs from the production environment. Estimated repair costs should be based on identifiable and assessable tasks, not an arbitrary percentage of the project price.
In Leave to Appeal 3525/14 LiveDNS Ltd. v. Shachar (May 29, 2014), the Supreme Court dismissed an application for leave to appeal against refusal to grant ex parte orders for seizure of computer evidence. The Court noted the absence of a sufficient evidentiary basis for the exceptional remedy and that, on the applicants’ own evidence, copying could prima facie be identified without seizing the hidden code. In a source code dispute, the need to seize computer evidence under an Anton Piller order must be justified by identifying the missing evidence and considering whether it can be obtained by less intrusive means.
Managing a Software Development Dispute Before Filing a Claim
When a development project runs into serious difficulties, the first step is to establish its legal and technical position. The parties should collect the agreement, successive versions of the specifications, quotations, change approvals, correspondence, timesheets and invoices paid. At the same time, the source code, version history, test results and defect records lawfully held by the customer should be preserved before further changes are made to the system.
An independent technical expert should assess which obligations have been fulfilled, which requirements remain unmet, the causes of the defects and the anticipated cost of completing the project. Based on the findings, a detailed demand can be addressed to the provider, identifying the alleged breaches, required corrections and deadlines for performance in accordance with the contractual and statutory mechanisms for cure and termination.
Before terminating the agreement, the customer should evaluate the commercial merits of continuing with the existing developer against transferring the project to another provider. This involves obtaining a quotation for completion, assessing whether existing deliverables can be reused and identifying what the original developer must deliver, including source code, technical documentation, databases and access permissions.
In many cases, the parties can negotiate an end to the engagement by separating the transfer of deliverables and continuity of business operations from their financial dispute. Such an arrangement should specify whether claims arising from earlier breaches are reserved or finally settled.
If negotiations fail, the contractual, technical and financial material collected will support the formulation of the causes of action, quantification of damages and preparation of expert evidence.